Calendars and Run Dates (School Days and Homework)

School Days

A school only runs on school days. Saturdays and Sundays are off, so are bank holidays and snow days, and now and then a Saturday catch-up lesson is added. A business calendar is that list: which weekdays work, which dates are holidays, and which extra dates count anyway.

from datetime import date

from pyscheduler.calendars import BusinessCalendar

uk = BusinessCalendar(
    "uk",
    weekdays=frozenset(range(5)),  # 0 = Monday ... 4 = Friday
    holidays=frozenset({date(2026, 12, 25), date(2026, 12, 28), date(2027, 1, 1)}),
    extra_days=frozenset(),
)

print(uk.is_business_day(date(2026, 12, 25)))  # False: Christmas Day
print(uk.previous(date(2026, 12, 29)))  # 2026-12-24
print(uk.next(date(2026, 12, 24)))  # 2026-12-29
print(uk.shift(date(2026, 10, 19), -1))  # 2026-10-16 (Monday back to Friday)
print(uk.nth_of_month(2026, 10, -1))  # 2026-10-30: last business day of October

previous and next always move at least one day. shift(d, n) takes n school-day steps (negative goes back; zero stays put). nth_of_month counts school days from the start (1, 2, ...) or the end (-1, -2, ...) of a month, and gives None if the month is too short. If a calendar has no working days at all, previous and next raise ValueError instead of searching forever.

The built-in ALL_DAYS calendar (named none) counts every day, and merge_calendars joins the holidays of several calendars into one.

Which Day's Homework Is This?

A job that runs at 02:00 on Tuesday is usually processing yesterday's work. Like a teacher marking Monday's homework on Tuesday morning, the job needs to know which day it is really for. That day is the run date.

  • same_day: the run date is the day the job fires. Tuesday's run is for Tuesday.
  • previous_business_day: the run date is the school day before the firing day.

On a Monday-to-Friday calendar, a 02:00 job with previous_business_day:

Fires on Run date
Tuesday Monday
Friday Thursday
Monday Friday

The Monday run processes Friday, because the weekend has no homework. The calendar also filters firings: if the firing day itself is not a business day, the job simply does not fire, so Saturday and Sunday never produce a second Friday run.

from datetime import date

from pyscheduler.calendars import ALL_DAYS, BusinessCalendar

weekdays = BusinessCalendar("weekdays", frozenset(range(5)), frozenset(), frozenset())
monday = date(2026, 10, 19)
print(monday)  # same_day -> 2026-10-19
print(weekdays.previous(monday))  # previous_business_day -> 2026-10-16
print(ALL_DAYS.previous(monday))  # no calendar -> 2026-10-18