Forecast (The Weather Report for Jobs)

"Probably Starting Around Six"

A weather forecast doesn't know what will happen. It looks at the pattern and says "rain around three". The forecast does the same for jobs: it reads the schedules, remembers how long each job usually takes, and says "this job will probably start around then".

  • A scheduled job is easy: it starts when its alarm rings.
  • A follower (a job that waits for others) starts when its slowest upstream is expected to finish: start plus the typical duration.
  • The typical duration is the median of the last 10 runs: line them up shortest to longest and take the middle one, so one freak slow day doesn't spoil the forecast. With no history, the forecast uses the upstream's start time.
import tempfile
from datetime import UTC, datetime, timedelta
from pathlib import Path

from pyscheduler.config import load_config
from pyscheduler.schedule.forecast import forecast

text = """
jobs:
  extract:
    command: run-extract
    schedule: "30 18 * * *"
  report:
    command: run-report
    depends_on: [extract]
"""
with tempfile.TemporaryDirectory() as folder:
    path = Path(folder) / "scheduler.yaml"
    path.write_text(text)
    config = load_config(path)

minute = timedelta(minutes=1)
start = datetime(2026, 10, 19, tzinfo=UTC)
end = start + timedelta(days=1)
past = {"extract": [10 * minute, 20 * minute, 30 * minute]}  # newest first
for entry in forecast(config, start, end, durations=past):
    print(entry.job, entry.expected_start.time(), entry.via)
# extract 18:30:00 None
# report 18:50:00 extract

The Small Print

  • The window is (start, end]: start is left out, end is included. Both must carry a time zone, or you get a ValueError.
  • Disabled jobs and manual-only jobs are left out.
  • A follower gets one entry per run date. It appears as soon as any upstream has an entry for its date, just like the real scheduler creates its run when the first upstream run shows up. Its start is decided by the upstream expected to finish last (via names it).
  • A follower whose upstream is inside the window is kept even if its expected start falls after end.
  • The forecast assumes the happy path: every upstream succeeds. The on: kind of a dependency is ignored, so a job that only runs on failure still appears.
  • Jobs caught in a same-run-date dependency cycle are skipped. A loop through an earlier run date (load needing its own run_date: -1) is not a cycle: it looks at a run that is already over.

The API (GET /api/forecast), pysched forecast and the timeline's ghost bars all use this one function.